Building Design Process (characterize or define each cell) |
|||||||||||
INTERIOR |
Pre- Design Conference
|
Planning & Program ming |
Concept Design submittal (10-15%) |
Design Develop. submittal (30-65%) |
Pre-Final submittal (90%) |
Final submittal (100%) |
Construc -tion Funded |
Construc -tion Award |
Construc -tion |
Beneficial Occu- pancy |
Post occu -pancy eva- luation |
Pre-Design Conference |
|
|
|
|
|
|
|
|
|
|
|
Generate Programming Documents |
|
|
|
|
|
|
|
|
|
|
|
Develop DD1391 & FF&E Cost Estimate |
|
|
|
|
|
|
|
|
|
|
|
Establish SID/FF&E Requirements |
|
|
|
|
|
|
|
|
|
|
|
Establish FF&E Acquisition Strategy |
|
|
|
|
|
|
|
|
|
|
|
Structural Interior Design |
|
|
|
|
|
|
|
|
|
|
|
Furniture Footprint Design |
|
|
|
|
|
|
|
|
|
|
|
Award /Initiate FF&E Design |
|
|
|
|
|
|
|
|
|
|
|
FF&E Pre-Design Conference |
|
|
|
|
|
|
|
|
|
|
|
FF&E Preliminary Submittal |
|
|
|
|
|
|
|
|
|
|
|
FF&E Presentation To Customer |
|
|
|
|
|
|
|
|
|
|
|
FF&E Final Submittal |
|
|
|
|
|
|
|
|
|
|
|
Submit To Contracting Authority For Funding |
|
|
|
|
|
|
|
|
|
|
|
FF&E Presentation To Customer |
|
|
|
|
|
|
|
|
|
|
|
Field Verification & Review Of SID |
|
|
|
|
|
|
|
|
|
|
|
Finish Submittals With Contracting Officer |
|
|
|
|
|
|
|
|
|
|
|
Procurement Of Furniture |
|
|
|
|
|
|
|
|
|
|
|
Furniture Delivery And Installation |
|
|
|
|
|
|
|
|
|
|
|
Photography Of Complete Interior |
|
|
|
|
|
|
|
|
|
|
|
Post Occupancy Evaluation |
|
|
|
|
|
|
|
|
|
|
|